东山站项目进展 Dongshan Marine Station Project Progress

项目进展(2014.12.30)
Project Progress as of December 30, 2014
此信息发布于:2015-1-10      浏览次数:340

20143月,东山临海实验与观测站一期工程主体建筑碧海楼完成施工与监理的招标工作。

20144月,签订二期征地协议,一、二期征地总面积达到87.5亩。

20147月,召开东山临海实验与观测站第一次国际咨询委员会会议。

201410月,主体大楼碧海楼开始基础施工。

The construction and supervision bidding for the first phase had been completed since March 2014.

         We had signed the protocol of phase land requisition which increased the area of land requisition to 14.4 acre in April 2014.

The first advisory committee meeting for Dongshan marine station was held at July 2014.

The construction of the main building foundation has started since October 2014.

一、二期征地范围

The land requisition for the first & second phase

基础施工

The construction of the main building foundation

   

国际咨询委员会议

The first advisory committee meeting for Dongshan marine station